Slab depth for an extension

For a ground-floor extension in Ireland, the concrete slab should be at least 150 mm thick, on at least 200 mm of compacted hardcore (Building Regulations TGD C). That's 350 mm before the insulation, the screed and the floor finish.

The total depth is worked back from the finished floor level of the house, so the new floor lines up with the old one. The insulation thickness comes from the U-value: 0.18 W/m²K, or 0.15 with underfloor heating (TGD L).

Free, no obligation. One local concrete contractor prices it, not five.

The build-up, layer by layer

LayerMinimum or rule
Floor finishPer the product
Screed65 mm floating sand and cement in a house; liquid screeds thinner
InsulationWhatever reaches 0.18 W/m²K, or 0.15 with underfloor heating
Concrete slab150 mm, thicker if the design needs it
DPM and radon barrierDPM continuous with the wall DPCs; radon barrier and sump in a High Radon Area
BlindingEnough to fill the voids
Hardcore200 mm, gas permeable (T2 Perm)

Matching the existing floor

The finished floor of the extension has to meet the house's floor, so the dig depth is set from the top down: the floor finish, the screed, the insulation, the slab and the hardcore. If the old floor has little insulation and the new one needs 0.18 W/m²K, the extension's floor zone can be deeper than the old one.

Where a step or a ramp isn't wanted, a thinner screed can help: liquid screeds go down thinner than sand and cement. See screed depth over underfloor heating on our sister site.

What else goes in before the pour

  • The radon sump: TGD C expects a standby sump in every new floor, with a sealed barrier in High Radon Areas
  • Drains and service ducts
  • Edge insulation at the walls
  • The hardcore docket, showing it meets S.R. 21 Annex E

Floors laid by the contractor who takes your call

Calls on this site ring JAM Floor Screeding: James Mulhall, based in Portlaoise, 25 years laying floors. Lines open Mon to Sat, 7am to 6pm. He pours concrete floors, slabs and foundations as well as screed. These are his jobs.

A sand and cement screed floor in a new build with insulated walls
Sand and cement screed, new build
A wide pumped screed floor in an empty commercial unit
Commercial unit, pumped screed
A screed pump and a worker in hi-vis outside a stone house being renovated
The pump on a stone house renovation

“JAM were punctual, professional and efficient and did an outstanding job on pouring our new floor as part of a renovation. Very highly recommend!”

David O'Keeffe, Google review

“Excellent work, laser level finish, neat and tidy worker, highly recommend.”

Cathal Kelly, Google review

“Top class work by james and his crew, highly recommend”

the duke, Google review

Quoted word for word from JAM Floor Screeding's Google reviews. Read them on Google

Get the job priced in 4 quick taps

Tell us about the job. It goes to one concrete contractor who covers your county, and they ring you to price it.

What's the job?

Pick the closest one. The contractor talks it through.

By sending, you agree to Concrete Contractors passing your details to one concrete contractor who covers your county, so they can contact you about the job. Privacy notice

Concrete contractors guides & price breakdowns

Straight answers to what people ask most: itemised costs, specifications, planning or grants, and what to check before you book.

More guides & resources: Concrete vs screed · Slab depth for an extension · Building Regulations for concrete · All guides & calculator hub · Technical & trade glossary · Frequently asked questions · All areas covered · About this site

Questions people ask

How thick should an extension floor slab be?

At least 150 mm of concrete under TGD C, thicker if the structural design needs it, on at least 200 mm of compacted hardcore.

How deep do I dig for an extension floor?

From the finished floor level down: the floor finish, the screed, the insulation, 150 mm of slab and 200 mm of hardcore. 350 mm of that is slab and hardcore.

What U-value does an extension floor need?

0.18 W/m²K, or 0.15 W/m²K where the heating is underfloor (TGD L 2022).

Does an extension need a radon barrier?

In a High Radon Area, a fully sealed barrier and a standby sump. Elsewhere, TGD C still expects a standby sump.

Concrete contractors across all 26 counties

Requests from all 26 counties go to one vetted local specialist who covers your county — from Dublin, Cork, Galway and Limerick to Kildare, Meath, Wicklow, Waterford and Donegal. Pick your county below for local prices, specifications and advice. Compare all areas covered →

Get a free quote for the job

Four taps and your number. One concrete contractor who covers your county rings you with a price. Nothing is booked until you say yes.